Featured Project
Access Dredging for Oil and Gas Industry with Beneficial Reuse of Dredge Material
| Service |
Hydraulic Dredging · Oil & Gas Support |
| Region |
Southeast Louisiana |
| Client Sector |
Private industrial and evergy |
| Timeframe |
June 2021 |
| Scale |
80,000 CY dredged (approx.) |
| Crew |
Supervision, dredge technicians, equipment operators, boat captains, and laborers |
The Challenge
A bayou providing the only marine access to a customer's energy infrastructure had silted in over years of natural sediment deposition. Water depth was no longer sufficient to float marine equipment to the location.
The channel and the area around the project site both had to be deepened prior to work taking place, and the dredge material had to be beneficially reused to comply with state and federal permits.
The Approach
U.S. Aqua mobilized a hydraulic dredge system and amphibious excavators to carry and spread material several thousand feet from the cut.
The crew ran 12-hour operations to reopen the bayou channel and clear the project site to required depth, with a marsh excavator and airboat supporting shoreline work and access. Dredged material was placed to build new marsh in an environmentally sensitive coastal environment.
Equipment Used
| 12" hydraulic dredge pump |
| Hydraulic power unit |
| Booster pump |
| 12 inch HDPE dredge pipeline |
| Crane barge |
| Marsh excavator |
| Air boat |
Complicating Factors
- Active pipeline corridors in the work area requiring careful placement and clearance
- Remote marsh access with no landside route, worked entirely on a full marine spread
- Long discharge run requiring booster staging
Results
- Bayou channel and project area restored to navigable depth
- Barge access achieved; client started work on schedule
- Dredged sediment beneficially reused to create new marsh, a habitat gain alongside the access work
Agencies We Serve
State & Regional Agency Experience
Coastal Protection & Restoration Authority (CPRA)
Marsh restoration, ridge restoration, and beneficial use projects under the Louisiana Coastal Master Plan.
State Port Authorities
Maintenance dredging, placement area capacity restoration, containment dike construction, and dredge material management for the Alabama State Port Authority, South Carolina port facilities, and other Gulf and Atlantic port operations.
Parish & County Levee Boards
Levee construction and rehabilitation, drainage canal maintenance, and flood protection earthwork for parish-level levee districts, regional flood control authorities, and county drainage boards.
State Departments of Transportation
Bridge approach work, waterway crossings, marsh and wetland fill, and access road construction in soft-soil terrain for LADOTD, MDOT, and other state DOTs across the Gulf Coast and Mid-Atlantic.
State Wildlife & Fisheries Agencies
Habitat restoration, marsh creation, and waterway maintenance projects for state agencies including the Louisiana Department of Wildlife and Fisheries (LDWF) on refuges, wildlife management areas, and public water bodies.
Regional Water Management Districts
Sediment removal, channel maintenance, and shoreline stabilization for regional water authorities, drainage districts, and conservation districts that manage Gulf Coast and Mid-Atlantic water resources.